Annual Capital Projects Program

Capital projects support the growth and reliability of our water system. The chart below shows the watermain projects scheduled to occur in 2009 if the City proceeds with their Operations and Sewer/Road Programs.

Capital Projects Map

Size: 437.5 KB

WUC Priority Projects

Street Dia. Length (m) 2009 Capital Budget
Woodland Avenue (Richardie to West Grand) 300/200 710 $408,250
Wyandotte Street East (Strabane to George) 300 540 $467,500
Strabane Avenue (Riverside to Wyandotte) 300 255 $467,500
Homedale (Tranby to Wyandotte) 300 1,300 $795,000
Riverside Dr E (Vanderbilt to Tecumseh Border) 200 2,590 $1,359,750
Continental (Malden to Cul De Sac) 200 813 $487,800
Malden Road (Lansing to Chappus) 300 1,410 $740,250
Riverdale (Wyandotte to Menard) 400 250 $250,000
Scofield (incl. Holburn/Wallace) (Howard to Holburn) 200 800 $460,000
Weaver (Ojibway to West of ETR) 300 240 $144,000
Rankin/West Grand (Grand Marais Road to Grand Marais Drain) 150/50 100 $80,000
Tecumseh Elevated Tower     $70,000
Hanna Elevated Tower     $50,000
Cathodic Protection (Various Streets)     $500,000
Sub Total: 9,008 $6,280,050

2009 - Operations Program

Street Dia. Length (m) 2009 Capital Budget
Ellis (Windsor to Lillian) 300/600 250 $414,750
Detroit (Sandwich (Russell) to Donnelly) 200 450 $247,500
Watson (Wyandotte to Little River) 200 760 $418,000
Ellis (Ouellette to Dougall) 200 265 $145,750
Victoria (Ellis to Erie) 200 850 467,500
Forest (Tecumseh to Ypres) 200 840 $462,000
Barrymore (Brock to Prince) 200 591 $325,050
Byng (Sydney to Seymour) 200 261 $143,550
Chilver (Seneca to Tecumseh) 200 390 $214,500
Chilver (Assumption to Niagara) 200 602 $331,100
Gladstone (Richmond to Ottawa) 200 528 $290,400
Whitney (Prince to Chappell) 200 417 $229,350
Wyandotte St West (Rosedale to Mill) 200 223 $122,650
Sub Total: 6,427 $3,747,350

2009 - Sewer/Road Program

Street Dia. Length (m) 2009 Capital Budget
Elsmere (Hanna to Giles) 200 955 $625,000
Westminister (Lassaline to Tecumseh) 200 832 $300,000
Coronation (Westminister to Ford) 200 225 $300,000
Prado (Riverside to Wyandotte) 200 370 $260,000
Virginia (Wyandotte to St. Rose) 200 180 $85,000
Ida (Somme to Memorial) 200 460 $100,000
Memorial (Kildare to Ida) 300 179 $100,000
Head (Kildare to Ida) 200 159 $100,000
Vimy (Elsmere to Alley West of Parent) 200 296 $50,000
Terminal (Parent to Elsmere) 200 193 $106,150
Parent (Terminal to Ypres) 300 685 $305,250
McKay (Pelletier to Tecumseh) 200 160 $84,000
Curry (Pelletier to Tecumseh) 300 164 $86,100
Pelletier (McKay to Campbell) 200 331 $173,775
McEwan (Pelletier to Leduc) 200 90 $50,000
Alexis (Alice to Tecumseh) 200 590 $324,500
Norman (Grand to Joinville) 200 515 $283,250
Partington (Tecumseh to College) 300 1,070 $630,000
Eastlawn (Edgar to Cul-de-Sac) 200 240 $140,000
Clemenceau (St. Rose to Grand) 200 755 $415,250
Sub Total: 8,449 $4,518,275

2009 City Major Road Projects

Street Dia. Length (m) 2009 Capital Budget
Ouellette (Park to Wyandotte) 300 425 $450,000
Howard / North Talbot 300   $400,000
Howard / CP Grade Separation 300   $200,000
Wyandotte (Florence to Clover) 400 250 $162,500
Sub Total: 675 $1,212,500
Grand Total 2009 Watermain Renewal Program: $15,758,175