Annual Capital Projects Program
Capital projects support the growth and reliability of our water system.
The chart below shows the watermain projects scheduled to occur in 2009 if
the City proceeds with their Operations and Sewer/Road Programs.
Capital Projects Map
WUC Priority Projects
| Street |
Dia. |
Length (m) |
2009 Capital Budget |
| Woodland Avenue (Richardie to West Grand) |
300/200 |
710 |
$408,250 |
| Wyandotte Street East (Strabane to George) |
300 |
540 |
$467,500 |
| Strabane Avenue (Riverside to Wyandotte) |
300 |
255 |
$467,500 |
| Homedale (Tranby to Wyandotte) |
300 |
1,300 |
$795,000 |
| Riverside Dr E (Vanderbilt to Tecumseh Border) |
200 |
2,590 |
$1,359,750 |
| Continental (Malden to Cul De Sac) |
200 |
813 |
$487,800 |
| Malden Road (Lansing to Chappus) |
300 |
1,410 |
$740,250 |
| Riverdale (Wyandotte to Menard) |
400 |
250 |
$250,000 |
| Scofield (incl. Holburn/Wallace) (Howard to Holburn) |
200 |
800 |
$460,000 |
| Weaver (Ojibway to West of ETR) |
300 |
240 |
$144,000 |
| Rankin/West Grand (Grand Marais Road to Grand Marais Drain) |
150/50 |
100 |
$80,000 |
| Tecumseh Elevated Tower |
|
|
$70,000 |
| Hanna Elevated Tower |
|
|
$50,000 |
| Cathodic Protection (Various Streets) |
|
|
$500,000 |
|
Sub Total: |
9,008 |
$6,280,050 |
2009 - Operations Program
| Street |
Dia. |
Length (m) |
2009 Capital Budget |
| Ellis (Windsor to Lillian) |
300/600 |
250 |
$414,750 |
| Detroit (Sandwich (Russell) to Donnelly) |
200 |
450 |
$247,500 |
| Watson (Wyandotte to Little River) |
200 |
760 |
$418,000 |
| Ellis (Ouellette to Dougall) |
200 |
265 |
$145,750 |
| Victoria (Ellis to Erie) |
200 |
850 |
467,500 |
| Forest (Tecumseh to Ypres) |
200 |
840 |
$462,000 |
| Barrymore (Brock to Prince) |
200 |
591 |
$325,050 |
| Byng (Sydney to Seymour) |
200 |
261 |
$143,550 |
| Chilver (Seneca to Tecumseh) |
200 |
390 |
$214,500 |
| Chilver (Assumption to Niagara) |
200 |
602 |
$331,100 |
| Gladstone (Richmond to Ottawa) |
200 |
528 |
$290,400 |
| Whitney (Prince to Chappell) |
200 |
417 |
$229,350 |
| Wyandotte St West (Rosedale to Mill) |
200 |
223 |
$122,650 |
|
Sub Total: |
6,427 |
$3,747,350 |
2009 - Sewer/Road Program
| Street |
Dia. |
Length (m) |
2009 Capital Budget |
| Elsmere (Hanna to Giles) |
200 |
955 |
$625,000 |
| Westminister (Lassaline to Tecumseh) |
200 |
832 |
$300,000 |
| Coronation (Westminister to Ford) |
200 |
225 |
$300,000 |
| Prado (Riverside to Wyandotte) |
200 |
370 |
$260,000 |
| Virginia (Wyandotte to St. Rose) |
200 |
180 |
$85,000 |
| Ida (Somme to Memorial) |
200 |
460 |
$100,000 |
| Memorial (Kildare to Ida) |
300 |
179 |
$100,000 |
| Head (Kildare to Ida) |
200 |
159 |
$100,000 |
| Vimy (Elsmere to Alley West of Parent) |
200 |
296 |
$50,000 |
| Terminal (Parent to Elsmere) |
200 |
193 |
$106,150 |
| Parent (Terminal to Ypres) |
300 |
685 |
$305,250 |
| McKay (Pelletier to Tecumseh) |
200 |
160 |
$84,000 |
| Curry (Pelletier to Tecumseh) |
300 |
164 |
$86,100 |
| Pelletier (McKay to Campbell) |
200 |
331 |
$173,775 |
| McEwan (Pelletier to Leduc) |
200 |
90 |
$50,000 |
| Alexis (Alice to Tecumseh) |
200 |
590 |
$324,500 |
| Norman (Grand to Joinville) |
200 |
515 |
$283,250 |
| Partington (Tecumseh to College) |
300 |
1,070 |
$630,000 |
| Eastlawn (Edgar to Cul-de-Sac) |
200 |
240 |
$140,000 |
| Clemenceau (St. Rose to Grand) |
200 |
755 |
$415,250 |
|
Sub Total: |
8,449 |
$4,518,275 |
2009 City Major Road Projects
| Street |
Dia. |
Length (m) |
2009 Capital Budget |
| Ouellette (Park to Wyandotte) |
300 |
425 |
$450,000 |
| Howard / North Talbot |
300 |
|
$400,000 |
| Howard / CP Grade Separation |
300 |
|
$200,000 |
| Wyandotte (Florence to Clover) |
400 |
250 |
$162,500 |
|
Sub Total: |
675 |
$1,212,500 |
| Grand Total 2009 Watermain Renewal Program: |
$15,758,175 |